Are you in the loop? Keep up with the latest by making sure you're subscribed to Community Announcements. Just click Watch and select Articles.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

How to automate closing the sub-tasks when a parent task is complete.

Hi All,

I appreciate the wider issue about why someone would not complete sub-tasks before completing the parent task. But I was wondering if automation could sort this. Have tried a few different automations below but when testing it does not seem to work. 

Any help would be appreciated.

Automation example .jpg

1 answer

1 accepted

0 votes
Answer accepted
Mohamed Benziane
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Mar 09, 2022

Hi @Dan Billingham 

Try with the condition "Issue fields condition" intead of subtask present

2022-03-09 16_09_40-Automation - The Jira of Champions.png

Thank you Mohamed,

This works now, much appreciated!

Hi Mohamed

 

I've used the exact same automation suggested but I get this error. What am I missing?

Screenshot 2023-02-07 140644.png

Hi,  Thembisa,
Maybe have a look at your workflow.
Can you transition to close/done from any status?

Hi Natasja

Only 3 statuses transition to done, will this work only if all statuses can transition to done?

Hi Tembisa,.

Yes, it would be best, then the sub-task can be closed/done from any status.