How to auto update all start/end dates if I change one linkd task start/end date within an epic?

Kate Cook
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 25, 2023

New to Jira so still learning. But all tasks in each epic are sequential (and linked), and I want to be able to set the number of days for each task and the first tasks start/end dates and have the rest automatically populate. Similar to MS project - I want to be able to manipulate schedule with number of days - is this possible in Jira? 

Started playing with automation - and got this far (see below) before I'm lost and don't know how to finish or even if I'm on track!

 

- When: Values change for

due date, start date

- If: linked issues present

types: all link types

- Then: Edit issue fields

start date 

 

The number of days was helpful for working through tasks so would be useful if we can have it in Jira too - but not essential! 

 

Any suggestions helpful please!!! 

1 answer

0 votes
Valerie Knapp
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
October 25, 2023

Hi @Kate Cook , welcome to the Atlassian Community and thanks for your question!

I always recommend that people check out the Jira automation template library. It is a free resource with a bunch of worked examples for automations. Normally you can find something that is relatively close to where you want to get to and then just modify slightly.

For your case, I found this - Jira automation template library | Atlassian

In your case, you could also, instead of copying the date from the issue that called the automation, you can also set a date with a smart value -

Jira smart values - date and time | Cloud automation Cloud | Atlassian Support

So you could say, when something is changed to update the date to the trigger issue date plus days / weeks / etc

Please take a look at these resources, if you haven't already, and let us know if we can be of more help.

Cheers

Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 26, 2023

Hi @Kate Cook -- Welcome to the Atlassian Community!

Adding to Valerie's answer...

Depending upon the specifics of your scenario, this may or may not be possible with automation rules.  If you provide a specific example of "before" and "after", the community can offer ideas.  Until then...

You describe the behavior of a tool like MS Project, which not only understands the dependency linking of items, each of which has a forecast, it can process them in a defined manner and order of updates (backward and forward).

I suspect that is not possible with automation rule branching in your scenario.  The reason is branches on more than one thing process in parallel, and so a rule cannot easily "walk the chain" of linkages.  A special case would be if each issue had one-and-only-one link in a specific direction.  Even then, the rule would be brittle because if it failed, it may not be re-startable.

There was a post from the Atlassian team a while ago about considering adding the feature you describe directly to the roadmap / timeline view, so editing one issue updates the chain.  I have not seen anything on that in a couple of years.

If you truly need capability like that in MS Project, you may want to check the Atlassian Marketplace for any addon apps.

Kind regards,
Bill

Like Kate Cook likes this

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events