Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

How not to double original estimate on parent and sub-tasks?

CARLA JEANINE TRINIDAD
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 8, 2024

Hi everyone,

Here's my current scenario:

I'm using Original Estimate on Backlog View as shown below. This helps during sprint planning. 

1.jpg

Added Original Estimate on Backlog view: 24hrs

Added Sub-task 1 with Original Estimate: 12hrs

Added Sub-task 2 with Original Estimate: 12hrs

Total hours on Parent ticket: 48hrs

2.png

By default, Jira sums the Original Estimate on the parent and on the sub-tasks. Unchecking the "Include sub-tasks" shows only the parent Original Estimate and not the logged hours on sub-tasks.

 

If I add sub-tasks with Original Estimates, It doesn't sum up on the backlog view. In my example above, having 24hrs on 2 sub-tasks will just show 0hrs on the backlog view.

3.png

What can I do to not double the estimates? Not specify the Original Estimates on sub-task level and just use it to log work hours? Is there a way to configure this (I am not Jira Admin in our company)?
I'd appreciate all answers. Thank you!

 

0 answers

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events