edit the end date of a sprint after completing?

How can I edit the end date of a sprint after completing the sprint?

2 answers

you can used the below api

put jiraserver/rest/greenhopper/1.0 /sprint/{spinrtID}

parameter : name=Iteration 2, id=337, startDate=12/Mar/14 8:13 AM, endDate=25/Mar/14 8:13 AM

Does this work for ondemand? Will try it out, thanks!

`jiraserver/rest/greenhopper/1.0/sprint/{sprintId}/edit/model` will give you a starting JSON object

Not possible using the UI. You might change the database directly, while that is not recommended.

Suggest an answer

Log in or Sign up to answer
TAGS

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you