edit the end date of a sprint after completing?

How can I edit the end date of a sprint after completing the sprint?

2 answers

you can used the below api

put jiraserver/rest/greenhopper/1.0 /sprint/{spinrtID}

parameter : name=Iteration 2, id=337, startDate=12/Mar/14 8:13 AM, endDate=25/Mar/14 8:13 AM

Does this work for ondemand? Will try it out, thanks!

`jiraserver/rest/greenhopper/1.0/sprint/{sprintId}/edit/model` will give you a starting JSON object

Not possible using the UI. You might change the database directly, while that is not recommended.

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Published Apr 18, 2018 in Agile

Top 10 Insights from the 12th Annual State of Agile Report

...challenges organisation’s experience in their efforts to adopt and scale agile.   Many people associate agility with complete flexibility. And that’s not necessarily true, as demonstrated by this finding....

316 views 1 3
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you