edit the end date of a sprint after completing?

How can I edit the end date of a sprint after completing the sprint?

2 answers

you can used the below api

put jiraserver/rest/greenhopper/1.0 /sprint/{spinrtID}

parameter : name=Iteration 2, id=337, startDate=12/Mar/14 8:13 AM, endDate=25/Mar/14 8:13 AM

Does this work for ondemand? Will try it out, thanks!

`jiraserver/rest/greenhopper/1.0/sprint/{sprintId}/edit/model` will give you a starting JSON object

Not possible using the UI. You might change the database directly, while that is not recommended.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Aug 21, 2018 in Agile

What's new this quarter in Confluence Server - August 2018

Hello Atlassian Community! My name is Ada , and I'm the Product Marketing Manager for Confluence Server at Atlassian. If you missed   our last post, we're transitioning to quarterly updates&nb...

165 views 0 1
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you