Always display estimate in hours

If I enter 8h for a task estimate it converts and displays as 1d 1h (because available hrs is 7). I just want it always to show hours - 8h.

Capture.JPG

 

Thx

Rick

1 answer

0 vote

Hi Rick,

From the JIRA Admin cog-> Issues-> Issue Features > Time Tracking, you can change the time display format, as shown in this picture:

Screen Shot 2017-12-10 at 9.44.33 PM.png

Hope it works,

Carlos

Carlos,

 

Thx for the reply. Yes that was exactly what I was looking for. Might clarify though that you have to Deactivate the Time Tracking in order to see the screen you presented. Once I figured that out worked like a champ.

Thx

Rick

I'm glad it worked!

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published May 14, 2018 in Agile

Marketplace Technical Collection Pages

You might have noticed something new on Marketplace in the last several months which was the addition of our new collection pages. We heard feedback that it can be hard to browse apps in Marketplace ...

63 views 0 4
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you