Are you in the loop? Keep up with the latest by making sure you're subscribed to Community Announcements. Just click Watch and select Articles.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Story points roll up

Hi,

I created a story and subtasks under the story. My team added task-level story points. Is there a way to automatically calculate the total story points of this story?

 

Thanks 

2 answers

1 accepted

3 votes
Answer accepted
Daniel Capizzi
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Oct 11, 2022

Hi @Hiti Verma

This can be done in Advanced Roadmaps using the "roll-up" feature! Please try selecting "View Settings" in the top left of your plan, then checking the "Others" box in the "Roll-up" section.

Screen Shot 2022-10-12 at 09.58.13.png

From there, you'll be able to see on your roadmap view the sum of all your sub-task story points rolled up to the story issue I've included a screenshot of what it should look like below - you can see the arrow pointing to the "8" indicates that it's a roll-up value. Screen Shot 2022-10-12 at 09.58.30.png

Let me know if you have any trouble getting that set up and I'd be happy to help out!

Cheers,

Daniel

If I were to use the "View Settings" and enable groups based on labels... is there a way to roll up the story points to these groups?

Currently, Advanced Roadmaps only rolls up story points to the highest issue type in the hierarchy, but not to groups.

For example, I have labeled some features tickets with a label and configured my View Settings in Advanced Roadmap, and any feature that has a certain label is grouped as  "Core Platform":

Screenshot 2023-06-01 at 4.49.35 PM.png

Like Yueji Huang_黄越己_ likes this

My current workaround is to export the data and perform the rollup in a spreadsheet, but this is suboptimal...

0 votes
Dan -minware-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Oct 11, 2022 • edited

Disclaimer: marketplace partner!

Hello @Hiti Verma -

This is a popular request that can be solved with minware. Our tool offers unique groupings and provides aggregate metrics for the tickets in that group:

1. Story Point Estimates

2. Dev Days

3. Total Tickets

all_tickets_flow.png

There may be a way to achieve this natively but I wanted to present this as an option as it is a frequent request. I hope you find what you are looking for and please let me know if we can help. 

 

Edit: make sure to see @Daniel Capizzi 's answer!

Dan -minware-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Jun 01, 2023

@Edwin Meijer - hope all is well! Saw your second post to Daniel and that's something we can definitely help with in minware. Let me know if you want to chat!