We are not a fully SCRUM team but we are trying to follow agile principles:
- 2 week sprints to iterate and track work
- Story points to estimate
Our manual calculations give us estimated finish milestones such as 5/5.
1. Should I use "target end" or "due date" of 5/5?
2. When I tried Due Date, the roadmap view did not show 5/5
3. How does the roadmap generate dates from story points?
Hi @Bea Tea
How does the roadmap generate dates from story points? it doesn't.
The timeline data is generated by the date fields you choose to use in your Plan.
Disclaimer: I'm talking about Cloud AR...am uncertain regarding non Cloud versions.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks @Curt Holley Maybe I read the info/tutorials wrong. I thought that it could generate some timelines based on Story point estimates.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.