How to: move multiple timelines in Jira Plans

Christian Brandl
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 12, 2024

 

How is it possible to move multiple timelines at the same time in Jira Plans?

Example: Delay in the project - all downstream tasks are also moved.

Unfortunately, it does not work via dependencies (blocked by or blocks). Also, as researched, the CTRL/STRG multiple selection does not work either.

Is there an easy way to move several tasks? Many thanks for your help!

Best regards Christian Brandl

1 answer

0 votes
Hans Polder _Devoteam_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 12, 2024

@Christian Brandl ,

Welcome to the community! I believe you should be able to accomplish this by doing the following:

1) Check the checkbox of one of the items in your plan

2) Then, while holding the SHIFT-key, select the checkbox of the upper/lower issue of your desired selection - it should multi-select like seen on the screenshot below

3) Click 'bulk actions' button above

4) Choose 'Dates'

5) Follow the prompts

Screenshot 2024-09-12 160846.png

Caveat: You'll likely be wanting to move the existing 'duration' of items (for instance, 2 weeks, or 4 weeks, etc). I think that'll be quite difficult this way, but you should give it a try!

 

Christian Brandl
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 16, 2024

Thanks for the Information!
But like you mentioned below - all timelines will be in the same date-range.
Important to me is, that I can shift all timelines with their space between. 
Means that they shall have their same duration, like: after workpackage A follows workpackage B.

stevenlee
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 10, 2024

I have the same question. Despite the fact JIRA could track dependency, but it does not seem to act like MS Project where moving one task would trigger cascade effect to the dependants.  