How is it possible to move multiple timelines at the same time in Jira Plans?
Example: Delay in the project - all downstream tasks are also moved.
Unfortunately, it does not work via dependencies (blocked by or blocks). Also, as researched, the CTRL/STRG multiple selection does not work either.
Is there an easy way to move several tasks? Many thanks for your help!
Best regards Christian Brandl
Welcome to the community! I believe you should be able to accomplish this by doing the following:
1) Check the checkbox of one of the items in your plan
2) Then, while holding the SHIFT-key, select the checkbox of the upper/lower issue of your desired selection - it should multi-select like seen on the screenshot below
3) Click 'bulk actions' button above
4) Choose 'Dates'
5) Follow the prompts
Caveat: You'll likely be wanting to move the existing 'duration' of items (for instance, 2 weeks, or 4 weeks, etc). I think that'll be quite difficult this way, but you should give it a try!
Thanks for the Information!
But like you mentioned below - all timelines will be in the same date-range.
Important to me is, that I can shift all timelines with their space between.
Means that they shall have their same duration, like: after workpackage A follows workpackage B.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.