Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

How should we do capacity planning and auto scheduling with multiple member kanban teams?

Kerner
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 21, 2022

We're working on moving to Advanced Roadmaps from Microsoft Project for our cross-team project planning and roadmaps. The issue we've come up with is that the autoscheduler and capacity settings don't seem to take multiple team members doing multiple projects simultaneously. 

Here's a simplified scenario:

  • Kanban Team A has 3 members who each have a capacity of 30 hours/week giving the team 90 hours of capacity
  • Project 1 is estimated at 30 days (assignee A)
  • Project 2 is estimated at 30 days (assignee B)
  • Project 3 is estimated at 10 days (assignee C)
  • Project 4 is estimated at 20 days (assignee C)

What we're seeing is that:

  • Advanced roadmaps rightly sets the team capacity at 11.25 days/week
  • Unfortunately it schedules the projects sequentially with: 
    • Project 1 taking 2.6 weeks 
    • Project 2 taking 2.6 weeks following project 1 
    • Project 3 taking less than 1 week following project 2 
    • Project 4 following project 3
  • It appears the assumption when autoscheduling is that all team members are working on the same effort as opposed to each team member working on different efforts
  • Having different assignees for the epics doesn't impact the scheduling

When assigned to different team members what we believe should happen:

  • Project 1 would take 8 weeks (30 days at 30 hours/week)
  • Project 2 would take 8 weeks (30 days at 30 hours/week) concurrently with project 1
  • Project 3 would take 2.6 weeks concurrently with 1 & 2
  • Project 4 would take 5.3 weeks starting after project 3, concurrently with 1 & 2
  • All projects would complete at the same time

The questions:

  • Is there a way to have capacity equally split among multiple epics within a team?
  • Is there a way to concurrently schedule work based on the assignee? 
  • Has anyone found a workaround other than single member teams? (this feels like an anti-pattern we don't really want)

2 answers

1 vote
Nataliya Vasyliv_Reliex_
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
April 26, 2022

Hi @Kerner 

Could be Team capacity a workaround for you? The ActivityTimeline plugin has a Team Timeline, that provides users of ActivityTimeline with an extra level of flexibility when it comes to planning team’s work, as it allows to schedule work not only for individuals but for the team as a whole.

ActivityTimeline provides a work scheme - a work schedule that can be assigned to a single individual or to a group of people, that defines their working days as well as the number of available hours during these days. 

Workload could be split between two or more issues. Via Bulk reschedule there is a possibility to schedule tasks based on the assignee. 

You can try a trial or we can provide a demo session for you if needed.
Best, Nataliya

0 votes
Kerner
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 21, 2022

Given this feature request, my guess is that there isn't a good option here.

https://jira.atlassian.com/browse/JSWCLOUD-20434

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events