The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How do I assign issues to a cross project release?

Annette Banes
Contributor
August 20, 2019

I have a portfolio plan with 3 project and several cross project releases that apply to all 3 projects. How do I assign the issues in the 3 projects to the cross project releases? 

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Earl McCutcheon
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 21, 2019

Hi Annette, 

Once you have created a cross project release in the Plan and associated the projects to the release as covered in "Creating and configuring cross-project releases" adding the issues to the release can be done either by setting the release in the "Releases: column:

Screen Shot 2019-08-21 at 4.23.39 PM.png

OR you can set the version in the issue directly via the Fix Version Field, below is a screenshot for the same issue in both the New issue view and The Classic view to highlight the difference in location:

Screen Shot 2019-08-21 at 4.28.30 PM.png    &   Screen Shot 2019-08-21 at 4.25.20 PM.png