How do I assign issues to a cross project release?

Annette Banes August 20, 2019

I have a portfolio plan with 3 project and several cross project releases that apply to all 3 projects. How do I assign the issues in the 3 projects to the cross project releases? 

1 answer

0 votes
Earl McCutcheon
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 21, 2019

Hi Annette, 

Once you have created a cross project release in the Plan and associated the projects to the release as covered in "Creating and configuring cross-project releases" adding the issues to the release can be done either by setting the release in the "Releases: column:

Screen Shot 2019-08-21 at 4.23.39 PM.png

OR you can set the version in the issue directly via the Fix Version Field, below is a screenshot for the same issue in both the New issue view and The Classic view to highlight the difference in location:

Screen Shot 2019-08-21 at 4.28.30 PM.png    &   Screen Shot 2019-08-21 at 4.25.20 PM.png

Regards,
Earl