I am trying to setup a project in JIRA Kanban template.
In advance roadmaps, I added all the estimates for each tasks and mapped dependencies among the tasks.
When I put in the start date for the first task and click on autoschedule, it doesnt create a right timeline with correct estimates.
Even if the estimate put in is 5 days for a particular task, the timelines populates with different estimates. So the dates I get for project start date and end date are not correct.
Hi @Shruti Rathore welcome to the Atlassian Community!
To auto-schedule issues in your plan:
By default, the Auto-scheduler schedules all of the estimated issues in your plan. If you want to schedule certain issues, select them using the checkboxes in the Scope section.
Navigate to Auto-schedule and configure the auto-schedule settings. Learn about the Auto-scheduler configuration options.
Select Preview results to see suggested changes, as shown above. The schedule bars of auto-scheduled issues and their corresponding issue details will be shown with purple stripes. Hover on a field to compare the current values against the suggested changes. The number of auto-scheduled issues will depend on the hierarchy levels you've chosen for the plan.
Select Accept changes to create your plan. The Auto-scheduler will not overwrite any issues that are in a sprint that’s currently active.
Make your changes, then select Review changes.
Have a look at the following documentation page for more info: How does Auto-scheduler in my plan work?
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.