Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Auto schedule selected issues

I want apply auto scheduling to specific issues within my plan, and I select those specific issues by applying the checkboxes in the scope section, but the auto scheduling is always applying to all of my issues in the plan. Is there anything else I should be doing/configuring for this to work? 

Thanks,
Andrew

Select

Select specific issues.png

Result

Auto schedule result.png 

 

1 answer

Same problem here. It looks like it is some common thing. There is another similar question 
How to Auto-schedule only some issues in Advanced ... (atlassian.com)