The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

due date of issue is auto-corrected to due date of sub-issue

Simone Hammerl
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 23, 2020

Hello all,

 

we created a Portfoltio with different boards and filters, and releases as input.

We wanna show the Sagsa (issues) with the defined due dates. As well the sub-issues (epics, user stories) and their due dates, end dates. 

Target is to see if the sub-isses run longer as the scheduled due date (or target end date) of the issue. To see if there is a delay by sub-issues. 

Problem is, that the due date of the issues is auto- changed to the last due date of the sub-issues... not keeping the defined due date of the issue itself.

 

How can I solve this?

 

Thanks so much for help!

 