So, basically, in the documentation, I found something like this:
when I look at my schedule, I also have releases with a fixed release date, but I don't get the red indicator which should tell me how much I'm overbooked. I only get the "bottleneck" info. While my release is overbooked. For some reason he just schedules it over the fixed release date, instead of trying to put everything IN the release and then saying "person X is overbook by Y days"
Hi!
I disn't wanted to add a new topic for the same question, so:
I have the same problem.
Here is what I have:
1 Portfolio plan with 1 project and 1 team. the team is overbooked for the releases for sure. But instead of showing the overbooked hours on the bars, the release finish date is moved to a later date.
I understand, that this is caused because of the grouping, but no grouping is selected, see :
What can be the reason?
Thank you, br
Daniel