Why are some issues set to "Later Release"

Edited

I have a plan created in Portfolio and release versions created weekly all the to the end of Q2 2019. However, my plan is assigning a lot of issues to the "Later Release" and not scheduling all the other releases I have created.

Has anyone had this problem before? Are my tickets too large, and that's why they get sent to the "Later Release"?

1 answer

1 accepted

0 votes
Answer accepted

Hi @Dan Casados Here is the  documentation that explains why items get assigned to Later Release.  It is likely that you are seeing one of the scenarios described.  

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Jira

Online AMA this week: Your project management questions answered by Jira Design Lead James Rotanson

We know that great teams require amazing project management chops. It's no surprise that great teams who use Jira have strong project managers, effective workflows, and secrets that bring planning ...

179 views 1 6
Read article

Atlassian Community Events