Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,644,725
Community Members
 
Community Events
196
Community Groups

Story points disabled in portfolio

In Portfolio,  I want to use story points for planning mode.   However on the Configure->Scheduling page the story points option button is disabled,  and I cannot select.    I cannot find out why this is.

Please help,  as only way for me to use Portfolio is if I can set it up to use story points

1 answer

3 votes
Martin Suntinger
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Jul 24, 2016

Hi Linda - this option gets disabled when you have a team set to Kanban, as for story point scheduling currently Portfolio requires the notion of a sprint and velocity. if you switch your teams to "Scrum", you should be able to switch to story points too. If your teams do Kanban but still estimate in story points, you could simply configure them to use "Scrum" with 1 week iteration length, and plan weekly. 

Hi, I had the same experience (could not use story points).  I had changed an existing plan to use a different board.  I could not use story points.  But when I deleted that plan, and made a new one, then I could use story points.  Is this normal?