Scheduling in Days

Hi All,

I am new to JIRA portfolio and am trying to schedule a "Project" . I am just interested in tracking at a high Level(Milestone Based planning) in Days.

I have created a few tasks under the Epic and have set dependencies. The first task's duration is 40 days but I am noticing that the "schedule end date" is not changing .

Observed behavior:

Task 1 - Estimate = 40 days, Sch. Start = 08/20/18, Sch End = 08/28/18

Expected Behavior :

Task 1 - Estimate = 40 days, Sch. Start = 08/20/18, Sch End = 10/20/18

 

Appreciate any insights/clues on this behavior.

1 answer

0 votes

One possibility here is that the default team working hours is being used to calculate a date indicating that the task can be completed in less time.

So for example your task might take 40 "person-days" but the default team capacity 200 weekly hours (e.g. 25 person days per sprint). One thing you could try is changing the team capacity to be a 40 hour week (you can achieve this by assigning a person to the team).

Regards,

The Portfolio Team

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,649 views 22 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you