Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,556,450
Community Members
 
Community Events
184
Community Groups

Portfolio for Jira - Weekends can't be excluded.

Edited

I want to plan my teams tasks without weekends being counted as work days.

The project is configured in the default workdays configuration.

The board is configured in the default workdays configuration.
The board is configured as Kanban.


I have defined estimates in days for the stories.
I have defined dependencies for the stories.
I have assigned the stories to a release (which I want to schedule).

I am using the improved planning interface of portfolio (Advanced Roadmaps) (Cloud)


---
=> In the planner view, I can see all parts of the release as expected. When I manually schedule the "bar" it can be assigned to weekends, which are annoyingly still visible in the calender timeline.Advanced Roadmaps Weekends.png

+ The placed story has to be adjusted by hand to the estimated length in days (single klick makes it 7 days long.... not e.g. 4 days long like defined.

+ The placed story (or the subtasks) can be assigned to WEEKENDS!!!!

---

=> Bonus Problem: Autoschedule (sometimes) ignores estimates and dependencies. It ignores the sequential scheduling and the estimated length of each task. 

Advanced Roadmaps Autoscedule.png

+The auto scheduler even displays his own errors (self aware?)
+The estimates are completely ignored
+The assignee is expected to be able to clone himself AND time-travel.

 

 



Help?

0 answers