Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Deleted user
0 / 0 points
Next:
badges earned

Your Points Tracker
Challenges
Leaderboard
  • Global
  • Feed

Badge for your thoughts?

You're enrolled in our new beta rewards program. Join our group to get the inside scoop and share your feedback.

Join group
Recognition
Give the gift of kudos
You have 0 kudos available to give
Who do you want to recognize?
Why do you want to recognize them?
Kudos
Great job appreciating your peers!
Check back soon to give more kudos.

Past Kudos Given
No kudos given
You haven't given any kudos yet. Share the love above and you'll see it here.

It's not the same without you

Join the community to find out what other Atlassian users are discussing, debating and creating.

Atlassian Community Hero Image Collage

Portfolio 3.0 doesn't update estimates?

Hello,

I have installed a Trial version of Portfolio New Interface (3.2). 

In my roadmap, if I move an issue around, it updates the Target Start and Target End fields of the associated Jira.  It does the same If I extend or shrink the expected duration of a task, but it doesn't update the time estimates of that Jira -- which is in days in my case.

Is that the expected behavior ? What is the link between logged work / remaining time / original estimates and the roadmap view?

I'm currently ending up with discrepancies as seen below:

image.png

Thanks!
JF

1 answer

1 accepted

0 votes
Answer accepted
Roi Fine Atlassian Team May 29, 2019

Hi @Jean-Francois Levesque,

My name is Roi, and I'm a product manager in the team. 

The target dates do not relate to the estimate field, nor the logged work / remaining time / original estimates. 

If your teams are working Scrum, Target dates could be inferred by the issues' sprint assignments. I.e: If you assign an issue a future sprint (one that was created in Jira) the target dates will be updated automatically. 

More info here: https://confluence.atlassian.com/jiraportfolioserver/scheduling-issues-967895238.html

I hope that helps,

Hello, @Roi Fine !

Is it clear that portfolio 3.2. doesn`t use estimates in auto-shedulling? 

Like I wrote here - I (can`t) don`t know how to analyze estimate progress in 3.1.  Can you help? 

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Jira Service Management

JSM June ask me anything (AMA)

Hello Community members! We’re wrapping up the end of JSM June with an Ask Me Anything (AMA) with the Jira Service Management product team. This is your chance to ask all your ITSM questions to o...

132 views 9 10
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you