You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hello,
I have installed a Trial version of Portfolio New Interface (3.2).
In my roadmap, if I move an issue around, it updates the Target Start and Target End fields of the associated Jira. It does the same If I extend or shrink the expected duration of a task, but it doesn't update the time estimates of that Jira -- which is in days in my case.
Is that the expected behavior ? What is the link between logged work / remaining time / original estimates and the roadmap view?
I'm currently ending up with discrepancies as seen below:
Thanks!
JF
My name is Roi, and I'm a product manager in the team.
The target dates do not relate to the estimate field, nor the logged work / remaining time / original estimates.
If your teams are working Scrum, Target dates could be inferred by the issues' sprint assignments. I.e: If you assign an issue a future sprint (one that was created in Jira) the target dates will be updated automatically.
More info here: https://confluence.atlassian.com/jiraportfolioserver/scheduling-issues-967895238.html
I hope that helps,