Parallel tasks for a single user

Hi Community,

 

I would like to have a user A be able to work in parallel on 2 tasks of 2 differents Kanban projects (lets say Task 1 and Task 2).

 

In Portfolio, I tried to create 2 distincts teams (Team 1 and Team 2), and added this user A in both teams, with 20 working hours per week in each.

I set up teams accordindgly for Task 1 and Task 2 with Team 1 and Team 2.

I thought that Portofolio would have scheduled parallel work for Task 1 and Task 2, but instead, User A will have to work on Task 1 first, then Task 2.

 

I would prefer that he works on Task 1 AND Task 2, at the same time.

 

How could I achieve that ?

 

Thanks all :)

0 answers

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,645 views 22 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you