Overlapping Active Sprints

I'm getting an error from Portfolio that I have multiple overlapping sprints, but when I look at the sprints, they are not actually overlapping. Is this a new bug or something I'm missing?Screen Shot 2018-01-02 at 4.37.30 PM.pngScreen Shot 2018-01-02 at 4.37.49 PM.pngScreen Shot 2018-01-02 at 4.38.05 PM.png

1 answer

1 accepted

1 vote
Answer accepted
Thomas Atlassian Team Jan 02, 2018

Hi @Dominic O'Connor,

 

The most likely issue is that your sprint DEMETER-RS-26 is in the past but is still active (not closed) saying that it is still running. As a result it is in fact overlapping EOS-RS-1.

If that makes sense, I'd advise to complete the DEMETER-RS-26 sprint and then reload / recalculate the plan to see if the error persists.

 

Cheers,

Thomas.

Yeah that seemed to do it. Overlapping was confusing nomenclature since the end date that we defined didn't actually overlap with the next sprint, but conceptually your explanation makes sense. Thanks!