In Jira Portfolio, I have broken down epics into multiple stories and prioritised. Portfolio is scheduling small stories above higher priority stories. Is there a way for Portfolio to stick to the priority order of stories? It is difficult to add dependencies, as I have so many epics and stories.
I have tried updating the scheduling setting for 'Minimum work package size' to different figures, but that doesn't seem to change anything.
Hello everyone, Hope everyone is safe! A few months ago we posted an article sharing all the new articles and documentation that we, the AMER Jira Service Management team created. As mentioned ...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events