Jira Portfolio resource allocation by skill set

Hi all, 

I think I know how to use Jira portfolio very well and for the most part, I get great value from it. But, I cannot quite get the skills set feature. 

Question: How can the team estimate their stories (on the backlog) and have those estimations "land" on the corresponding skill set in portfolio without having to copy/pasting them?

Example: 

  1. I have 2 iPhone devs and 2 Android devs resources, all belong to the same Scrum team
  2. They take the tickets and estimate them. Example: 4 Android stories, 5 iPhone dev stories
  3. I go to the portfolio, refresh the data and Portfolio assigns any ticket to any of them regardless of what the skills are on the resources. 

Am I really supposed to go down the list, ticket by ticket and copy the "Original estimate" value and paste it under the appropriate skill set? Really? 

 

I must be doing something wrong. I hope 

 

Any help here would be immensely appreciated 

0 answers

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,319 views 20 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you