Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,295,628
Community Members
 
Community Events
165
Community Groups

JIRA Portfolio - Assigned Sprint not in the Plan

Hi,

We are using JIRA for managing different Scrum boards but we are handling all Scrums into same project. For this reason, we've been adding the Sprints manually so we can sync all scrums to follow the same pacing. 

As far as I understand, Portfolio could use Teams or Shared Teams capacity to calculate the plan (Sprints) based on our Release Dates. However, we won't be able to use "Auto-Schedule" before getting the backlog stablished.

Thus, we would like to assign by the PORTFOLIO what would be the Sprint to address some of the issues in the backlog. However, when we have the Sprint assigned by the PROJECT , we are getting "Assigned Sprint not in the Plan"

Question: How can we assign the Sprint into Portfolio with Sprints created manually into the project? 

1 answer

1 accepted

0 votes
Answer accepted
Raathi Atlassian Team Jul 25, 2019

Hi Bruno,

From Portfolio 3.5 onwards, the plan would display sprints even though if the sprint is not in the plan. Which version of Portfolio are you using?

Regards,
Raathi

Hi @Raathi ,

Thanks for the reply.

I think we've been using 3.5.0.

How can I double check this information? 

Thanks

Hi, I have double checked with the team and it is version 3.4.0. 

Thanks

Hi @Raathi , How can I do that?

I'm using now version 3.9.0 but could not get the Sprint value set with the project sprint.

 

Best,

Raathi Atlassian Team Sep 16, 2019

Hi Bruno,

If your plan has scrum board as an issue source, then the sprints from those boards should appear in your plan and you can assign an issue to a sprint by clicking the sprint dropdown.

But if your plan has project as an issue source, then the sprints won't be available because the sprints belong to a board and not to a project.

But if you assign a sprint to an issue through Jira and then include that issue into a Portfolio plan, and if the sprint that is assigned to the issue is not in the plan (because you haven't included the scrum board the sprint belongs to), it will be displayed as an external sprint.

Regards,
Raathi

Like # people like this

If you select Sprint dates within Inferred Dates but have selected Project as your issue source (i.e., sprints not available), what dates will they default to if there's no start/end dates applied? 

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Posted in Jira Service Management

Jira Service Management Documentation Opportunities

Hello everyone, Hope everyone is safe! A few months ago we posted an article sharing all the new articles and documentation that we, the AMER Jira Service Management team created. As mentioned ...

304 views 0 9
Join discussion

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you