You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hi,
We are using JIRA for managing different Scrum boards but we are handling all Scrums into same project. For this reason, we've been adding the Sprints manually so we can sync all scrums to follow the same pacing.
As far as I understand, Portfolio could use Teams or Shared Teams capacity to calculate the plan (Sprints) based on our Release Dates. However, we won't be able to use "Auto-Schedule" before getting the backlog stablished.
Thus, we would like to assign by the PORTFOLIO what would be the Sprint to address some of the issues in the backlog. However, when we have the Sprint assigned by the PROJECT , we are getting "Assigned Sprint not in the Plan"
Question: How can we assign the Sprint into Portfolio with Sprints created manually into the project?
Hi Bruno,
From Portfolio 3.5 onwards, the plan would display sprints even though if the sprint is not in the plan. Which version of Portfolio are you using?
Regards,
Raathi
Hi @Raathi ,
Thanks for the reply.
I think we've been using 3.5.0.
How can I double check this information?
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Raathi , How can I do that?
I'm using now version 3.9.0 but could not get the Sprint value set with the project sprint.
Best,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bruno,
If your plan has scrum board as an issue source, then the sprints from those boards should appear in your plan and you can assign an issue to a sprint by clicking the sprint dropdown.
But if your plan has project as an issue source, then the sprints won't be available because the sprints belong to a board and not to a project.
But if you assign a sprint to an issue through Jira and then include that issue into a Portfolio plan, and if the sprint that is assigned to the issue is not in the plan (because you haven't included the scrum board the sprint belongs to), it will be displayed as an external sprint.
Regards,
Raathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you select Sprint dates within Inferred Dates but have selected Project as your issue source (i.e., sprints not available), what dates will they default to if there's no start/end dates applied?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.