You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
How can I plan project management in JIRA portfolio. I have stages likes design, implementation, test, but from project start to project end I need project management. How would I do that?
There are basically two options:
1) Use stages and turn off "stage/sprint constraints" in the plan settings (in the Scheduling section) - this will allow stages to run in parallel if there is capacity.
2) Use releases rather to model start and end dates or phases of project acticities, such as an analysis phase. Releases can have overlapping start/end dates. Break up the work packages accordingly in order to assign them into these releases (phases)
I'd need a bit more context to really judge if these are viable options and what are pro's and con's, so this is quite high-level input based on previous implementations we saw.