How is overload calculated?

Hi,

How is overload calculated?

Capture5.PNG

Is it the teams capacity in the 23 extra days? 

 

Regards

Louise

1 answer

0 votes

Hello Louise,

That view in question from your screenshot, is the Release report. The release is scheduled to end in another 23 days because the work assigned to a release is larger than the available team capacity, and this makes the release turn red.

In this release report view, the capacity is calculated using the team's velocity and the scheduled work for the release. For example, the team can finish a maximum of 30 story points in each sprint, the capacity will be overloaded if the work assigned to a release that has a fixed end date sometime in the next sprint are estimated more than 30 story points.

Some additional details on the settings can be seen in:

Regards,
Earl

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,645 views 22 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you