there are options for setting fixed dates or letting portfolio calculate the start date for you...
the fixed option is the only one that actually seems to work. The other options have no affect. I feel like I am missing something obvious but has anyone else had luck with this feature?
Hey Brad,
Are you referring to the start date and end dates of releases?
If yes, having a fixed start and end date will allow you to identify if all the items within this time period can be released on schedule.
Having Portfolio calculate this for you is a way to identify the possible release date with all the items you would like to complete.
Please take a look at https://confluence.atlassian.com/jiraportfolioserver/configuring-release-dates-802170565.html
Regards
Bhushan
Thanks - yes I understand generally how it supposed to work. But the different options did nothing to change dates really or show me a different outcome.
However, it turns out that some of my epics had start and finish dates already set by someone unbeknownst to me, so it was influencing the schedule outcome. Once I removed those constraints it solved my issue. Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello everyone, Hope everyone is safe! A few months ago we posted an article sharing all the new articles and documentation that we, the AMER Jira Service Management team created. As mentioned ...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.