Hi there,
I've created two custom date fields for 'Expected Start Date' and 'Expected End Date' for a stack of issues I've created and when I move them over to Portfolio, I want those dates to auto-populate the 'Target start' and 'Target due date'. How do I do this?
Separately, how do I stop Portfolio from creating 'Scheduled start' and 'Scheduled end' dates that seem arbitrary? I just want to use the dates I've manually entered and see those in the roadmap view.
Thanks
To see this feature in action check out our recent dependencies demo here: https /www.youtube.com/watch?v=eQu5VsUqyZA Keeping on top of your dependencies is a key part of ensuring project success....
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events