Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,559,781
Community Members
 
Community Events
185
Community Groups

Capacity Forecast taking exceptions into account

Hi

Does anyone know how to adapt the given capacity of an individual team member and therefore see the sprint capacity forecast. This was easily done in portfolio by going to the team section and adding exceptions for each member. With out this function the road-map tool lost a lot of power. 

 

thanks for the help.

 

 

1 answer

0 votes
Earl McCutcheon
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Jun 19, 2020

Hello @David Milford ,

Thanks for reaching out and in the new interface for Advanced Roadmaps, the scheduling for capacity is now based on the entire teams capacity for a more macro view rather than a micro view of the schedule, and Individual capacity was removed in favor of team capacity and is covered in more detail in the "Changes in the Improved interface" documentation:

Managing capacity

Previously, you'd be able to plan the individual capacity of your team members.

In the improved interface, individual capacity planning is replaced by team capacity planning. When auto-scheduling a plan, the total capacity of a team to complete the work being scheduled will be taken into account. To do this, you must directly set team capacity in your plan.

And Additional details in the "Future releases and limitations" documentation under the "Removed functionality" section:

Shared people settings – Since individual capacity planning is not supported, any configured settings for global availability and absences and team availability and exceptions will not apply to plans with the improved interface.

Regards,
Earl