I set up multiple sprints to map out a large body of work. I want to push back all the dates by two weeks. In other words, I want to insert a sprint in front of all of the sprints I created. Is this possible without having to open each future sprint and manually editing the dates?
Hey @Charlotte Pelz
I found a few references Edit multiple issues in bulk.
I did a quick test in my own instance and found that you can only update the Sprint field value.
If you create the new sprints with the new date you can then bulk update the issues into the new sprints.
I hope this helps a bit.
Let me know if you have further questions.
Thanks,
Brittany
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi everyone, We’re always looking at how to improve Confluence and customer feedback plays an important role in making sure we're investing in the areas that will bring the most value to the most c...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.