Hi all,

Currently, i'm using newest version of portfolio and create a plan with source is a board from jira. 

When update estimation of a ticket from Jira -> that updated is sync to Portfolio. But when updating assignee from Jira, this updated is not sync to Portfolio.

I already click refresh and Calculate button.

How can i do to make assignee updated to Portfolio when changing from Jira

4 answers

0 votes
Kerkko Pelttari July 3, 2018

Same problem. Using Jira cloud and the portfolio plugin.

Dima Rastaturin July 3, 2018

I figured that out. There should be an estimation in the ticket, otherwise it won't be synced (because Portfolio cannot schedule it). Also, good to check "Scheduling options" in the settings. 

0 votes
Dima Rastaturin April 15, 2018

I have the same issue. 

0 votes
Tuan Lam June 29, 2017

hi shantanu,

Thank you for your reply. I'm sure 100% assignee member is team member in portfolio plan. (on the top left, there are scope/release/team).

0 votes
Shantanu bhosale June 29, 2017

Hi Tuan,

Check that assignee in jira is a Team member of your portfolio plan.