I've been using Jira Advanced Roadmaps in the new interface for a month or two. Am now starting to experiment more with scheduling and dependencies.
From my experiments, it seems that JAR only acknowledges and displays the "blocks/is blocked by" links between two items. There are many alternative link types, for example, "has to be done before" or "has to be finished together with", which are in some ways more descriptive than "blocks". However, as far as I can tell, only "block" links are shown on JAR as linking two issues.
Is it possible to show link types other than "blocks" on JAR?
Which link types affect how the auto-scheduler works?
Thanks!
The 'Blocks/is blocked by' issue link is the default one being considered by Advanced Roadmaps, but it is possible to add/remove issue link types to be loaded and considered as dependencies by Advanced Roadmaps.
Documentation on this: https://confluence.atlassian.com/advancedroadmapsserver/configuring-issue-dependencies-802170496.html
Cheers,
Thomas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
So just to be clear:
Is that right?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello everyone, Hope everyone is safe! A few months ago we posted an article sharing all the new articles and documentation that we, the AMER Jira Service Management team created. As mentioned ...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.