Hi everyone,
I would like to create a monthly scheduled rule with Epic and Tasks which have Sub-tasks. How can I link Tasks (Issues) to the Epic?
If I create a branch it doesn't give me to add one more level a branch with subtasks for the recent created issue.
What are the options?
I found a similar question
https://community.atlassian.com/t5/Jira-questions/How-can-I-create-a-Epic-on-a-schedule-and-then-create-subsequent/qaq-p/759810
Thanks!
Hello @Natalia Golikova
Thank you for reaching out.
Per your description, I understand that you want to schedule an automation rule to create a pre-configured number of Epic, Tasks and Sub-tasks (Linked to each other) at the start of the month. Is that correct?
To achieve that, you can configure three rules and, using a common field value, make each one to be triggered by the other in a waterfall basis, properly creating the related tasks and sub-tasks as you need.
These would be the exact steps to achieve your need:
Let us know if this is what you are looking for or if you have any questions.
@Petter Gonçalves Thanks a lot! It works!
Does this work for Next Gen projects?
@Petter Gonçalves I did and rechecked everything, but ...
Can anyone tell me where am I going wrong?
Link for all images.
Hello @Michael Trice and @Dr Sudhir Ajja
The steps above are only applicable to Classic projects, so it might not work for Next-gen projects.
For Next-gen, you must use the Parent field instead of Epic link to link both Epic and task.
Let us know if this information helps.
Does the automatically created task make trigger at all? I tested this. I thought maybe this wouldn't work. I did a simple test. The first automation created a task. Second automation triggered when first task is created and created another task if task's reporter is Automation for Jira. This didn't work.
Maybe when creating a task, the trigger only works if we using the user interface. I don't know.