We are looking to make some project management in Jira Work Management simpler for our team. In short, as a project manager, I want the ability to update a "Due Date" OOTB field and have linked items adjust their due date based on the LOE field (# days) and the due date of the original ticket.
Some thoughts:
- I've seen a lot of articles about this but when I look at the smartvalues, I'm having a hard time implementing the condition of the LOE.
- Example: ticket-1 has a due date of 2/14/2023, there is also ticket-2 which is linked as "must be done after" ticket-1. The LOE on ticket-2 is 5 so I would want the due date on ticket-2 to be 2/14/2023+5d so 2/19/2023 (and I don't want it to count weekends).
- I've started on a few automations but keep coming back to issues.