Dear Community,
We've definitely all worked with the simple ToDo, In Progress, Waiting (For Customer, For something...), Test, Done Status structure. However, I am very careful with due dates and tracking tasks, and I want to do the following.
Whenever one of the tasks is updated to the status "Waiting", I want the Due Date to update its value, to however long the waiting status was changed, for example, if the Due Date was tomorrow which is 11/14/23 and I changed it to Status "Waiting" for 2 days, I want the due Date to change to 11/16/23, and same for hours, months, etc.
I tried Jira Automations, but I can't seem to figure it out.
I think a lot of people would find this helpful 
Thanks in advance!