I have a timeline in a construction project that I have to move dates on my issues constantly. I am looking to see if there is anyway that attached dependencies can be locked in place so that an issue moves and chronologically the dependency moves and dictates a new schedule of time.
Have you looked at the Auto-schedule feature of Advanced Roadmaps?
https://support.atlassian.com/jira-software-cloud/docs/auto-schedule-issues-on-your-advanced-roadmaps-timeline/
And here is another community post on that topic:
https://community.atlassian.com/t5/Advanced-Roadmaps-questions/Automatic-re-scheduling-of-tasks-with-delayed-dependencies/qaq-p/1405856
Otherwise you would need to build an Automation rule to update the dates of dependent issues when their predecessors change.
@Bill Sheboy provides some suggestions on using Automation rules in this post
https://community.atlassian.com/t5/Advanced-Roadmaps-questions/Automate-updating-of-start-and-due-date-based-on-delayed/qaq-p/1830252