Hi everyone, I would like to display projects more precisely in the timeline view. So, I have two questions:
1.Is it possible to add both dates (start date and due date) in each item in the checklist?
2.Is it possible to display checklist items in the timeline view?
Hi @Jarek
Using checklists doesn't give you either 1 or 2.
I have a method I use to give more precision and flexibility for such applications. I would have a parent/child relationship. So you have a deliverable and tasks within a checklist of that deliverable. When an item is added to tasks checklist, use automation to convert it to a card in list tasks and link them together. This now means you can add dates to the tasks and they can be linked back to the overall deliverable. Adding a label will give you the capability to filter against each deliverable. Here are some mockups:
Basic board set-up:
With filters applied to show tasks only for deliverable 3:
You can also see overall progress by opening the deliverable card:
Timeline view, with filter applied:
Can also be used effectively with calendar view
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.