The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Can you embed a production schedule into a Trello card?

Meghan Pirozzoli
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 8, 2017

I am a creative services project manager that works at a tech company. I interface directly with Business Units (BU) on their marketing requests and then take those requests to our internal graphic designers/design team to implement. 

Besides creating a checklist,  is there a way to add a pre-set schedule within a card? 

See example of what we are trying to achieve below. 

 

11/7 - Content recieved by Project Manager

11/9 - Content edited by Copywriter

11/10 - BU approved copy. Copy ready for layout.

11/14 - BU review copy/design layout

11/15- Design team makes edits

11/17 - BU conducts final review.

11/19 - FINAL DELIVERABLE DUE  

 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Francis Peixoto
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
April 5, 2018

If those actions are always the same on each card, you could use custom the date fields powerup to display this information per card.