helo everyone, i have problem with jira report. i estimate for task in sprint. but when i running sprint, i can't see a burndown report. please help me urgent !
Welcome to the Atlassian Community!
Assuming it is a Company-managed scrum or kanban
1> we using subtask, it not working for burndown and burnup chart, right?
2> we will hide task when done in last column, it mean all task in close sprint will not show in active sprint. so velocity can't show it, right?
1. Burndown is a function of sprints. Sub tasks (in Jira) are part of a story, not sprint items. So sprint estimation on sub tasks is nonsense. Do not do it (other estimation is fine, just not sprint/scrum)
2. If you hide it, then by definition, you cannot report on it.
@Fabio Racobaldo _Herzum_
could you help me please?
Help you with what? We've already explained what you're doing that needs to change.
Recommended Learning For You
Level up your skills with Atlassian learning
Learning Path
Get the most out of Jira
Start with basic Jira terms and navigation. Then, discover how to effectively organize work and customize your Jira experience.
Learning Path
Atlassian tools and practices for developers
Reduce context switching by making Jira more efficient, and apply collaboration best practices for streamlined team operations.
Atlassian Certified Associate
Jira Essentials certification
Validate your knowledge of key Jira concepts like using work items, spaces, boards, and Rovo.