Hello.
Can someone explain me what is the different between following time spent fields and how do you use them on Projects?
FYI: I know how to add to them to Issue screens and customize them.
Company manage project, Jira Admin access, Jira standard Pricing plan.
Thank you.
Solved! Go to Solution.
@Craig Nodwell Thank you so much for this answer.
I'm not sure if this answer is fully correct. It does indeed add up the time spent on child stories of the Epics but it does NOT include time spent on its sub-tasks, even not if you checked the box "include subtasks".
A bit strange because the time spent is added to the time spent of the story but NOT added to the Epic level with the field ∑ Time Spent
Coming back to this and what @jeroen.wilmes already stated, this is all weird, how should one use that data for reporting of time really spent top-down through the hierarchy?
Could you please elaborate on this @Craig Nodwell ?
Support suggested to vote for this already existing feature request:
Recommended Learning For You
Level up your skills with Atlassian learning
Learning Path
Get the most out of Jira
Start with basic Jira terms and navigation. Then, discover how to effectively organize work and customize your Jira experience.
Learning Path
Atlassian tools and practices for developers
Reduce context switching by making Jira more efficient, and apply collaboration best practices for streamlined team operations.
Atlassian Certified Associate
Jira Essentials certification
Validate your knowledge of key Jira concepts like using work items, spaces, boards, and Rovo.