Hello,
I have a question about prioritizing short but not urgent tasks.
On the one hand, there are critical tasks (such as system downtime or sales order stalled) or tasks that are less urgent but have a long duration of work, while on the other hand there are tasks that are not urgent (critical) but have very short working hours.
The departments that request these tasks can't wait a long time until the other tasks ahead are finished.
The question is how to prioritize tasks?
Are there any methods that help or support this issue?
Thank you.
These are really two different streams of work that should be surfaced and treated as such.
One stream sounds like a good fit for a first in first out queue in a Service Desk.
The other stream sounds like a more traditional effort where planned work is prioritized and flows across boards.
I would keep these separate and either split to two teams, or offially reduce the capacity/velocity of the build team to account for this stream of unplanned work.
Recommended Learning For You
Level up your skills with Atlassian learning
Learning Path
Get the most out of Jira
Start with basic Jira terms and navigation. Then, discover how to effectively organize work and customize your Jira experience.
Learning Path
Atlassian tools and practices for developers
Reduce context switching by making Jira more efficient, and apply collaboration best practices for streamlined team operations.
Atlassian Certified Associate
Jira Essentials certification
Validate your knowledge of key Jira concepts like using work items, spaces, boards, and Rovo.