Hello  I am suddenly not able to set dates anymore into WBS Gant . I am getting this error

 

Error occurred for the following reason. Please reload page.
Bad Request Field 'customfield_19018' cannot be set. It is not on the appropriate screen, or unknown

All my dates previously entered have been removed and are blank now. and each time an entering a date I am getting this error.

In my issues I have the Start date and Finish date (WBS Gantt_Chart) all set.

When I click on Open WBS Gantt-chart start date and finish date and baseline as well are all empty.

How should I be able to retrieve the Date in my issues into my Gantt chart ?

 

2 answers

Suggest an answer

Log in or Sign up to answer
1 vote
Charlotte Santos
Contributor
April 1, 2025

Hi @Jeff Brazzolotto

Thank you for posting! I’m Charlotte from WBS Gantt-Chart support team.

Is this project with the missing dates a Team-managed project?

If so, this issue must be happening due to API specification changes in Atlassian Cloud, which began rolling out in late February 2025, team-managed projects can now only retrieve data from fields that have been explicitly added to the project.

As a result of this restriction, if fields such as the start date are not added to the team-managed project, WBS Gantt-Chart for Jira will be unable to retrieve their values.

Therefore, it’s important that you add to the project the same fields that are configured in your Global Issue configuration, to check that follow the steps below:

  1. Click the gear icon ⚙️ to open Jira settings;
  2. Select Apps;
  3. Find WBS Gantt-Chart in the left column and select Issue;
  4. There you will be able to see which fields you use:
    Global-Issue-Configuration.png

Make sure to add the fields in your configuration to the project. For more information on that, and a video with the step-by-step, please refer to our documentation here: Start Date and Other Gantt-Chart Data Missing in Team Managed Project

I hope this clarifies things out for you, however don't hesitate to share your doubts or questions about the app. We’ll be happy to help you! 😉

If you prefer, you’re welcome to contact us directly through our Support Portal.

 

0 votes
Valerie Knapp
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 1, 2025

Hi @Jeff Brazzolotto , welcome to the Atlassian Community and thanks for your post. 

Please open a support ticket to the vendor, who should be able to help https://marketplace.atlassian.com/apps/1211768/wbs-gantt-chart-for-jira-enterprise-project-management?hosting=cloud&tab=support .