Tâm. Nguyễn Thanh April 5, 2023

I tried to create a rule with "Multiple project" scope to move an issue to DONE when all linked issues have DONE:

Capture4.PNG

 

And I found that this rule has the reverse effect like this:

Project A - Task 01 has bellow linked issues:

+ Project B - Task X

+ Project B - Task Y

=> As we expected, when Task X and Task Y move to DONE then Task 01 will be DONE, but if we move Task 01 to DONE it also makes Task X and Task Y move to DONE

 

Please help to resolve the situation.

Thanks,

1 answer

1 accepted

1 vote
Answer accepted
Trudy Claspill
Community Champion
April 5, 2023

Hello @Tâm. Nguyễn Thanh 

After the Trigger add a Condition to stop the rule if the issue that transitioned to done was in Project A.

Screen Shot 2023-04-05 at 11.07.15 AM.png

Tâm. Nguyễn Thanh April 9, 2023

Thanks, Trudy so much, It worked !

I also found another solution is to use the link type: issue in project B block issue in project A (blocked)

Capture5.PNG

Like Josh likes this