we have started sprint 67 which has issues in review which need to be closed and be part of Sprint 66. Is there a way to retrospectively moved the review/closed tickets to a closed sprint so that velocity/burn down/burn up reports include the data from those tickets?
No, because that would mean your sprint report is wrong. You didn't complete those things in the sprint.