The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

What determines the value / format of Delivery Status field?

Seth Mason
Contributor
July 11, 2022

I've seen the value of Delivery Status be:

  1. A State (To Do, In Progress, Backlog..)
  2. Three numbers (#ToDo, #InProgress, #Done)

 

What determines if the field should display the name of the state versus the three numbers?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

2 votes
James Traxler
Contributor
July 11, 2022

What I have observed is...

  1. If you have one item in the delivery tab of the idea, then delivery status shows the state of that item.
  2. If you have two or more items in the delivery tab of the idea, then you see the numbers.
Tanguy Crusson
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
July 12, 2022

Yep, that's correct, thanks!