The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Matrix view: date in x-axis possible?

Carlo Lammers
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 6, 2026

Hi fellow community,

I would like to create a graph/matrix showing the evolution of the expected workload (= number in the list view) of all the ideas as a function of time/date (=start date & target date in the list view).

Any workarounds or suggestions to make this possible?

Thanks!

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Jet
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 9, 2026

Thanks for your question - that's a cool usecase! 

Matrix view doesn't support date fields, so you won’t be able to create exactly that graph natively.

If your “expected workload” is stored in a numeric field, then you could create a timeline view which groups by the field that represents workload. This won’t give you a numeric curve, but it does show how high‑effort ideas are distributed over time. 

This is the simplest in‑product option if you mainly need a visual sense of when heavy vs light work is happening.

Hope this helps! Best,

Jet