The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to handle large multiteam/multiphase IT programs in Product Discovery

hroy
Contributor
September 26, 2024

We are trying to use Product Discovery to capture teams impacted at the Product Discovery stage, but we are realizing that we would need more Product Discovery tickets as the feature elaborates. Is there any learning from other customers that we can reuse here to keep a reign on the number of Product discovery tickets that we might end up creating for 1 value statement. We dont want to recreate our Jira in Product Discovery as well. Any guidelines of creating Product Discovery tickets that we can reuse? pls help. thanks 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Adrian.Lester
Contributor
September 27, 2024

Whenever we identify that some work is best achieved by delivering in multi-phase / iteratively we create 1 idea per phase/iteration (usually clone the original).  This lets us move each phase independently, and helps keep Jira clean and uncluttered with 'future stuff'.

 

The multi-team thing we handle by linking multiple delivery tickets (across the various teams) to avoid recreating Jira in JPD.