Fellows,
I am managing multiple projects in Jira, But I have never been able to generate Burndown chart from Jira successfully.
My projects set-up > Classic Scrum
Backlog structure > Versions > EPics > Story Cards / Tasks > Subtasks
Hours assignment > Sub Tasks has hours, and Story Cards has Points (Where 1 point = 9 hours). Hours are assigned under the field "Original Hours."
Sprint Duration > 3 Months ( We have a proprietary methodology, where Sprint is called an iteration. We are in 2nd iteration.
How is burndown chart generated > burn down chart is generated using "remaining hours at x-axis", "project duration at Y-axis".
But burndown is getting generated only for cards in-progress. Cards in "Todo" state are not picked up for remaining hours.
Needed > I want to generate burndown chart using Original hours at X-axis and Duration on Y-axis. But this is not generating anything, Redline that represents remaining hours is at zero and Green Line is not appearing at all.
Please help me with this problem. I have been struggling to resolve this problem for the last three months, and I am not able to generate burndown reports. Which makes our management think Jira is a useless tool and they are wasting money on it.
Best
Amit C
Recommended Learning For You
Level up your skills with Atlassian learning
Learning Path
Improve user experience across Jira with global settings
Learn how to set up and configure a Jira site, manage Jira permissions, and configure Jira apps and integrations.
Learning Path
Streamline projects across Jira with shared configurations
Build Jira work items with reusable configurations called schemes, and reduce administrative work with automation.
Learning Path
Become an effective Jira software project admin
Set up software projects and configure tools and agile boards to meet your team's needs.