Hello every one,
I don't know how use the time to describe my story and my subtasks.
I have 2 developers. My story have 2 subtask, a subtask for my developer 1 which is estimated at 3d and a subtask for my developer 2 which is estimated at 1d. My developer works in same taime so my story is estimated at 3d (the longer time, not the sum of each substask !)
How do you do it?