At a new company planning for growth and the vision is to use JIRA for project management of complex hardware/firmware/software/server developments (not exactly an Agile environment).
The "Roadmap" provides a high level view of what is going on but if management is used to a MS Project view there are some major differences.
+ The subtasks don't show as schedule items, though I can see them if I select a task
+ The dependencies don't seem to drive the dates (lots of details around how this does or could work - subtasks rolling up to tasks, rolling up to Epics, editable at all levels, planned vs actual, ...)
Does the fact that there are 3rd party apps (Big Picture, Structure, ....) suggest JIRA doesn't do this natively (or at least not well?)?
Maybe the Roadmap will be good enough to manage along with the project board - experience?
While I used JIRA for bug tracking in the past, I've never set up the projects so any suggestions welcome. Hoping for a bit of a discussion on best practices.
Recommended Learning For You
Level up your skills with Atlassian learning
Learning Path
Become an effective Jira admin
Manage global settings and shared configurations called schemes to achieve goals more quickly.
Streamline Jira administration with effective governance
Improve how you administer and maintain Jira and minimize clutter for users and administrators.
Learning Path
Become an effective Jira software project admin
Set up software projects and configure tools and agile boards to meet your team's needs.